REQUEST FOR PROPOSAL FOR GENERAL CONTRACTORS TO RENOVATE SINGLE FAMILY HOMES
Addendum No 1
NOTICE TO GENERAL CONTRACTORS
The work to be performed at the property identified below includes furnishing all labor, materials, supplies, tools, equipment and services required and necessary to perform and complete the construction work described herein and more specifically identified in the attached Construction Documents prepared By Simon Architectural Group, p.a. The bid Information, contact information and documents attached are indicated below. The construction work will be performed at the properties indicated below and are individually owned.
IT IS STRONGLY RECOMMEND THAT EACH GENERAL CONTRACTOR INVITE THEIR SUB-CONTRACTORS TO THE MANDATORY PRE-BID.
Important Dates & Times
Mandatory Pre-bid: Monday, August 6, 2012 (See times Below)
RFI Cutoff Date & Time: Monday August 13,2012 No later than 5:00 P.M.
Bid Date & Time: 11:00 A.M. Tuesday, August 21, 2012
|
Click Links Below to View and Download Documents
|
||||||
|
Time |
Address |
Specification Manual |
Certification Forms |
Bid Forms |
Construction Documents |
Reports |
|
2:30 P.M |
2457 Pinecrest Ct. WestPalm Beach,FL33406 |
|||||
|
3:15 P.M |
2393 Florida Mango Rd. WestPalm Beach,FL33406 |
|||||
|
4:00 P.M |
4066 Aster Ct.Lake WorthFL33461 |
|||||